Johan Sverdrup derrick installation

HLV Uglen successfully performed lifting operations on behalf of Nymo AS for installation of Johan Sverdrup drilling derrick structures

img 6024
Ugland Construction was awarded by Nymo AS (part of The J.J. Ugland Companies) the drilling derrick lifting contract for the Johan Sverdrup project.

 
The scope included the following items from the transportation vessel at Nymo quay onto the skid-base:




Upper and lower section were discharged from the MV Damgracht which transported the derrick sections from Korea to Grimstad. HLV Uglen’s main boom was used for the discharge operations.
 
For the installation of derrick lower part, upending and installation of the hydra-racker and installation of derrick upper part onto the skidbase, Uglen’s 126 meter high lift boom was used.  All three installtions took place 3rd  and 4th of March 2017.
 
The high lift boom sections are normally stored at Ugland’s storage site in Forsand. The high lift boom sections was transported on barges to the lifting site and erected before the lifting operations
 

Our services are executed in compliance with the highest international standards of safety and quality. In addition to cumpulsory marine codes our HSSEQ is certified by DNV according to: